REASON FOR DISCHARGE DELAY

The reason why a PATIENT with a Discharge Ready Date who no longer meets the ‘Criteria To Reside’ in a Hospital Bed , has not been discharged from a Hospital Provider Spell .

Description

The reason why a PATIENT with a Discharge Ready Date who no longer meets the 'Criteria To Reside' in a Hospital Bed, has not been discharged from a Hospital Provider Spell.

The REASON FOR DISCHARGE DELAY  should be recorded when the PATIENT has not been discharged from the Hospital Provider Spell and has incurred one or more overnight stays since being assessed as having 'No Criteria To Reside', and the recording of the Discharge Ready Date.

The REASON FOR DISCHARGE DELAY may change during the period of time during which discharge is delayed, and such changes should be submitted in the Healthcare Operational Data Flows Data Set: Acute - Current.

National Codes

Code Description
A01

Hospital process - Awaiting ALLIED HEALTH PROFESSIONAL review of need for supported discharge

A02 Hospital process - Awaiting  CONSULTANT  or other Registered Medical Practitioner  review of need for supported discharge
A03

Hospital process - Awaiting referral to Care Transfer Hub for supported discharge

A04

Hospital process - Awaiting Patient Transport Services

A05 Hospital process - Awaiting medicines to take home, discharge letter or other discharge documentation
A06 Hospital process - Remaining in hospital due to infection prevention and control restrictions
A07 Hospital process - Awaiting formal decision to discharge (including diagnostic test results)
B01

Wellbeing concerns - PATIENT, family, Carer  or Care Worker  concerns over discharge readiness

B02 Wellbeing concerns - Ongoing safeguarding concern
B03 Wellbeing concerns - Awaiting determination of mental capacity
B04 Wellbeing concerns - Issues with discharge destination readiness
C01 Care Transfer Hub

process - Awaiting confirmation of immediate care needs and Discharge Pathway

C02 Care Transfer Hub

 process - Awaiting necessary referrals by Care Transfer Hub

C03 Care Transfer Hub

process - Awaiting confirmation of funding eligibility

D01

Interface process - Home based rehabilitation, reablement or recovery service arrangements still underway (Discharge Pathway 1)

D02

Interface process - Other home-based social care service arrangements still underway (Discharge Pathway  1)

D03

Interface process - Other home-based community health service arrangements still underway (Discharge Pathway 1)

D04

Interface process - Housing provision arrangement for homelessness still underway (Discharge Pathway 0 or 1)

D05

Interface process - Bed-based rehabilitation, reablement or recovery service arrangements still underway (Discharge Pathway 2)

D06

Interface process - Residential or Care Home Services with Nursing  arrangements still underway (Discharge Pathway 3)

D07

Interface process - End of life care including Fast-Track Continuing Healthcare arrangements still underway (Discharge Pathway 1 or 3)

D08 Interface process - Further action required by receiving provider
D09 Interface process - Homeless with no recourse to public funds
D10 Interface process - Self-funded care package arrangements still underway
D11

Interface process -  PATIENT, family, Carer or Care Worker choice discussions on package still underway

D12 Interface process - Out of area discharge arrangements requested but not completed
E01

Capacity - Home-based rehabilitation, reablement or recovery services not yet available (Discharge Pathway 1)

E02

Capacity - Other home-based social care services not yet available (Discharge Pathway 1)

E03

Capacity - Other home-based community health services not yet available (Discharge Pathway 1)

E04

Capacity - Housing provision not yet available (Discharge Pathway 0 or 1)

E05

Capacity - Bed-based rehabilitation, reablement or recovery services not yet available (Discharge Pathway 2)

E06

Capacity - Mental health admitted patient care not yet available (Discharge Pathway 2)

E07

Capacity - Residential or Care Home Services with Nursing  not yet available (Discharge Pathway 3)

E08

Capacity - End of life care including Fast-Track Continuing Healthcare not yet available  (Discharge Pathway 1 or 3)

E09

Capacity - Housing adaptations not yet completed (Discharge Pathway 1 or 3)

E10

Capacity - Equipment and associated training not yet delivered (Discharge Pathway 1 or 3)

E11

Capacity - Awaiting restart of existing social care arrangements (Discharge Pathway 0)

Also Known As

This attribute is also known by these names:

Context Alias
Plural REASONS FOR DISCHARGE DELAY